Installation day is treated as a formality. The engineer arrives, the instrument is unpacked and connected, somebody signs a form, and the laboratory starts using it the following week.
That is a missed opportunity, because installation is the one moment when the supplier is physically present, motivated to finish, and has not yet been paid the final instalment. Whatever is not resolved that day gets resolved by telephone over the following months, if at all.
## Before the engineer arrives
Most bad installations were decided weeks earlier.
Confirm the site requirements in writing and check them against reality: floor space with the manufacturer's clearance at the back and sides, bench loading if it is heavy, power supply and phase, earthing, water quality and drainage if needed, ambient temperature range and the air conditioning to hold it, and network access if the instrument connects to your LIS.
Ambient temperature is the one most often missed. An analyser specified to 30 degrees, installed in a room that reaches 34 in May, will drift and nobody will connect the two.
Ask for the pre-installation checklist and complete it before the delivery date rather than on it. An engineer who arrives to find no dedicated power point will leave and come back next month.
## What should happen on the day
**Physical installation and levelling**, with the clearances actually left rather than promised.
**Power protection connected.** Stabiliser and UPS in place and tested, not planned. In this region this is not optional, and connecting the instrument to raw mains "for now" is how boards get damaged in the first month.
**Full functional verification.** Not just switching on. Run the manufacturer's start-up checks and record the results.
**Calibration and quality control.** Calibrate the assays you will actually run, and run controls at every level. Keep the printout.
**Performance verification.** This is the step most often skipped and the one accreditation requires. Precision — the same sample run repeatedly, within-run and between-run. Accuracy — comparison against your existing method or against assayed material. Linearity across the reportable range. Carryover, where relevant.
Do this while the engineer is present. If the instrument does not meet its claimed performance, that is a conversation to have with someone standing in your laboratory, not over email in a fortnight.
**Reference intervals and reportable range** established or verified, and documented.
**LIS interface tested end to end** — a real sample, ordered in the LIS, run on the analyser, result returned and validated. Not a demonstration of the connection.
## The training question
Insist that training happens on your samples, with your staff, over more than an afternoon.
A single session on installation day, watched by whoever happened to be free, is not training. Ask for a defined number of staff, a defined duration, and a return visit a few weeks later once people have real questions — which is when training is actually absorbed.
Get the names of who was trained recorded, because that record is the start of your competency file.
## What to leave with
The user manual and service manual in a language your staff read. Application sheets for every assay. The installation and performance verification records. The maintenance schedule, with the daily, weekly and monthly tasks written out. A list of consumable parts that fail predictably, and their part numbers. Service contact details, including the individual engineer, and the escalation path.
And the warranty terms in writing, with the date it starts. Warranty from delivery and warranty from commissioning can differ by weeks.
## Before you sign
Read the acceptance certificate. Signing it usually means the instrument met its specification, and it frequently triggers the final payment.
Do not sign it because the engineer is waiting and it is 6 pm. If something is outstanding, write it on the form. A qualified acceptance is a normal thing to issue and it is the last point at which you have leverage.
We install and commission equipment across Bihar and Jharkhand, and we would far rather spend an extra half day at commissioning than field the consequences for the next two years.